Your Virtual Facility - Specifications as Shown
Design Specifications
Building Code: Current Indiana Requirements
Wind Load : 85 mph
Seismic Zone : 2
Building Specifications - Manufacturing Area
Framing: Gable, Interior Columns
Width: 200
Length: 250
Eave: 28
Roof Cover: 24 ga. Standing Seam Roof
Wall Cover: 26 ga. Exterior Wall Panel w/ Kynar 500 Finish
Trim: Alum. Gutters and Downspouts
Insulation: 6 Fiberglass Batt Roof, 4 Fiberglass Batt Walls
Accessories: 2 Loading Docks, w/ Overhead Doors,Manual, Insulated
Roofing Insulation and Ceilings
New Gutters and Downspouts
4 Wall Insulation , 6 Ceiling Insulation
Interior Walls Separating Manufacturing Area From Office Area
Foundation Perimeter Insulated With 2 Rigid Insulation
Area Above Ceilings to be Insulated with 6 Batt
Acoustical Ceilings in Office Areas
2x4 Standard Lay-in Tiles and Grid
Ceilings in Pre-Engineered Building to be Exposed
24ga . Standing Seam Roof, 20yr. Warranty
Exterior Doors:
Qty.(4) 3070 Steel Insulated w/ Locksets
Qty. (2) Overhead Doors , 8x8, Manual Insulated Steel
Interior:
Concrete -Furnish and Install all Required Concrete Work
6 Thick , 4,000psi, Wire Reinforced Slab in Manufacturing Area ,4 in Office Area
Equipment Pads as Negotiated
Flooring- Sealed Concrete in Manufacturing Area, Vinyl Floor and Carpet in Office Area
Painting - Painted, Gypsum Board Interior Partitions in Office Area
Interior of Manufacturing Area to be Painted and Exposed
Plumbing/ HVAC:
ADA Approved Fixtures
Water Heater, Mop Sink,Hose Bibbs
HVAC 25 Tons Office Area
Ductwork,Economizer,Fresh Air Exhaust
1 Exhaust Fan in Each Restroom
All Gas Piping
Unit Heaters in Manufacturing Area
Electrical:
New Underground 3-Phase Service, Size to be Determined
Lighting -400w Metal Halide in Manufacturing Area,
2 x 4 Recessed Florescent Fixtures in Office Area
Exit and Emergency Lights
Switches and Receptacles Per Code
Wiring to HVAC Equipment
Electric Service for Specific Equipment Not Included
Offices:
Interior Partitions
Exterior Walls to Have 8 Liner Panel on Interior, Gyp. Board. In Office Area
Interior Partitions to Be 3 5/8 Steel Studs w/ Fire Rated Gyp. Board
Wall Separating Office From Manufacturing to Be Two Hour Fire Rated
Interior Doors To be Flush Wood ,Knock Down Frames, Includes All Hardware
Project Costs:
Building: $ 1,826,000
Site Improvements: $ 150,000
Land Costs: 10ac $ 100,000
TOTAL: $ 2,076,000
Completion Time
Construction plans can be completed within 30 days,upon final approval of design
Permits, approvals - 30 days
Construction can be complete in
180-210 days, weather dependent
Back to Top